2020
Company fully owned by:
signed a financing agreement for a total amount equal to € 58,1 Mln (Base Facility of € 54,0 Mln and DSRA Facility of € 4,1 Mln) in relation to 23 operating hydro power plants with aggregated installed capacity equal to 46 MW, with:


2019


in joint venture with Leitner was awarded the tender for the concession, construction and management of a new cableway and other facilities on the ski slopes of “Cortina 2021 - Alpine World Ski Championships”, for a total investment equal to € 22,0 Mln
2019
Energiae S.r.l., FD Holding S.r.l. and Risso Energia S.r.l.
sold the 100,0% quotas of
owning respectively (i) a district heating network and (ii) an operating cogenerative biomass power plant with total Installed Capacity equal to 1 MWe, located in Piemonte Region, to:
2018
Energia Valle Cervo S.r.l.
Company fully owned by:
signed an amendment to the existing financing agreement for a total amount equal to € 15,8 Mln, in relation to 3 operating hydro power plants with total Installed Capacity equal to 5,0 MW and located in Italy, with


2017
Company fully owned by:
signed a financing agreement for a total amount equal to € 58,0 Mln (Base Facility of € 57,0 Mln and VAT Facility of € 1,0 Mln) in relation to 17 operating hydro power plants with a total annual expected production equal to 110 GWh, with:
2016
purchased, through an auction process promoted by Milan Court, the business as going concern composed by roughly 1.100 service contracts for administrative and maintenance activities over a PV portfolio with Installed Capacity roughly equal to 13,5 MW originally owned by:
2015
Consortium composed by the following cooperative companies:
signed a project financing loan agreement for € 7,33 Mln (Senior facility of € 5,92 Mln, VAT facility of € 0,41 Mln and Net Working Capital facility of € 1,0 Mln) for the financing of a 144 beds nursing home for the geriatric patients with:
2014
signed a project financing loan agreement for a total amount equal to € 16,5 Mln (Senior Facility equal to € 12,4 Mln, Extra Costs Facility equal to € 1,0 Mln and VAT Facility equal to € 3,1 Mln), in relation to a 4,99 MW solid biomass power plant located in Italy with:
2013
as Mandated Lead Arrangers (MLAs) jointly with:
as Guarantor of the Financing structured a project financing loan agreement for a total of € 42,4 Mln (Senior facility of € 40,4 Mln and VAT facility of € 2,0 Mln), in relation to the construction of a 38 MW wind farm located in Italy, with:
2012
signed a project financing loan agreement for a total amount equal to € 104,0 Mln (Senior facility equal to € 90,2 Mln, Grid Infrastructure Facility equal to € 9,3 Mln and VAT facility equal to € 4,5 Mln), in relation to the construction of a 74 MW wind farm located in Italy with:
2012
as Mandated Lead Arranger, jointly with:
structured and signed a non recourse project financing loan for a total amount equal to € 15,4 Mln (Senior facility equal to € 13,9 Mln and VAT facility equal to € 1,5 Mln), in relation to the construction of 2 photovoltaic power plants on greenhouses located in Italy with a total Installed Capacity equal to 3,88 MW with:
2012
signed a project financing loan agreement for a total amount equal to € 5,1 Mln (Senior facility equal to € 3,6 Mln, VAT facility equal to € 0,9 Mln and Working Capital facility equal to € 0,6 Mln), in relation to the construction of a 1 MW biogas power plant located in Italy, with:
2011
acquired the 100,0% of 6 operating wind farms in Apulia region for a total Installed Capacity of 143,3 MW, from:
with the transaction BKW increases up to 100% its previous participation in the 6 wind farms, already owned through a 33% participation in Fortore Wind, joint venture set up in 2009 between Fortore Energia Group and BKW
2011
as Mandated Lead Arranger, jointly with:
Structured and signed a non recourse project financing loan for a total amount equal to € 35,6 Mln (Senior facility of € 34,2 Mln and VAT facility of € 1,4 Mln), in relation to the construction of a 23,6 MW wind farm located in Italy with:
2011
signed a project financing loan agreement for a total amount equal to € 11,2 Mln (Senior facility equal to € 10,0 Mln and VAT facility equal to € 1,2 Mln), in relation to the construction of 5 photovoltaic power plants located in Italy with a total Installed Capacity equal to 3,63 MW, with:
2011
as Mandated Lead Arranger, jointly with:
structured and signed a non recourse project financing loan for a total amount equal to € 24,6 Mln (Senior facility equal to € 22,1 Mln and VAT facility equal to € 2,5 Mln), in relation to the construction of a 7,76 MW PV plant located in Italy, with:
2010
signed a project financing loan agreement for a total amount equal to € 4,9 Mln (Senior facility equal to € 3,6 Mln, VAT facility equal to € 0,8 Mln and Working Capital facility equal to € 0,5 Mln), in relation to the construction of a 1 MW biogas power plant located in Italy, with:
2010
as Mandated Lead Arrangers (MLAs) jointly:
structured and signed a non recourse project financing loan for a total amount equal to € 53,1 Mln (Senior facility equal to € 50,6 Mln and VAT facility equal to € 2,5 Mln), in relation to the construction of a 37,5 MW wind farm located in Italy, with:
2010
signed a project financing loan agreement for a total amount equal to € 15,7 Mln (Senior facility equal to € 14,0 Mln and VAT facility equal to € 1,7 Mln), in relation to the construction of 5 photovoltaic power plants located in Italy with a total Installed Capacity equal to 4,6 MW, with:
2009
as Mandated Lead Arranger, jointly with:
structured and signed a non recourse project financing loan for a total amount equal to € 90,8 Mln (Senior facility equal to € 88,0 Mln and VAT facility equal to € 2,8 Mln), in relation to the construction of a 66,0 MW wind farm located in Italy, with:
2008-2004
3 Acquisitions: (1) in Spain the brick production business from Grupo Valforsa, (2) the 100,0% share capital of Ceramicas Estructurales Group, operating in the building materials industry from Grupo Uralita and (iii) in Serbia the business for brick production from Fit Becej.